2017
Date |
Project |
Vendor |
Invoice Number |
Invoice Total |
1/16/2017 |
On Call |
Wessler |
367.35 |
|
1/15/2017 |
On Call |
Wessler |
2,546.87 |
|
1/18/2017 |
Stormwater/Phase 1 Study Report MS4 |
Wessler |
29775 |
2,345.94 |
1/18/2017 |
01 Study Clean Comm. |
Wessler |
29779 |
1,740.64 |
1/18/2017 |
On Call |
Wessler |
29735 |
582.50 |
2/1/2017 |
Rate Study |
Peters Municipal Consultants |
12511 |
1,860.34 |
1/18/2017 |
Phase 3/Misc. |
Wessler |
29849 |
2,032.26 |
2/07/2017 |
Tree Removal |
TLC Tree Service |
43861 |
5,000.00 |
2/7/2017 |
Culvert Work |
Smith Projects |
App 2/Culvert Work |
30,125.00 |
2/16/2017 |
Phase 3/Misc |
Wessler |
29940 |
515.53 |
2/16/2017 |
Phase 3/Plan Review |
Wessler |
29939 |
1,421.25 |
2/16/2017 |
Phase 1/Study Report MS4 |
Wessler |
29938 |
1,545.00 |
2/17/2017 |
Phase 3/Misc |
Wessler |
29953 |
4,047.50 |
2/17/2017 |
Phase 3/Misc |
Wessler |
29954 |
6,035.00 |
3/11/2017 |
Stormwater/Tree Removal |
TLC Tree Service |
378393 |
2,500.00 |
3/01/2017 |
Rate Study |
Peters Municipal Consultants |
12512 |
2,930.48 |
3/14/2017 |
On Call |
Wessler |
30020 |
318.75 |
3/14/2017 |
On Call |
Wessler |
30021 |
3,227.50 |
3/17/2017 |
Stormwater |
Wessler |
30048 |
4,298.03 |
3/17/2017 |
Stormwater |
Wessler |
30049 |
326.24 |
3/20/2017 |
01 Study Clean Comm. |
Wessler |
30060 |
1,627.49 |
3/10/2017 |
St. Francis Demo |
Shrewsberry |
2108506 |
705.05 |
4/3/2017 |
Culvert Piping/Woodmont Court |
Smith Projects |
80609 |
1,500.00 |
4/3/2017 |
Site Prep |
Environmental Remediation |
FW-16-07-0240 |
9,980.00 |
4/3/2017 |
Street Sweeping Cards |
Dalton Sauter |
1779 |
1,335.00 |
4/3/2017 |
Root Work |
Dukes Root Control |
12735 |
$9,515.46 |
4/3/2017 |
Phase 4 |
Wessler |
30071 |
$10,527.59 |
4/3/2017 |
Phase 1 |
Wessler |
30048 |
$4,298.03 |
4/3/2017 |
Phase 3 |
Wessler |
30049 |
$326.24 |
4/17/2017 |
Catch Basin Grate |
Utility Supply |
1213948 |
$445.94 |
4/17/2017 |
Storm Sewer 534 S.4th |
Ace in the Hole |
13125 |
$5,300.00 |
4/17/2017 |
Rebuild Pit Wall |
Ace in the Hole |
13124 |
$4,400.00 |
4/17/2017 |
Rate Study |
Peters Municipal Consultant |
12513 |
$869.13 |
5/1/2017 |
Phase 3 Task 17 |
Wessler |
30125 |
$2,184.22 |
5/1/2017 |
Phase 3 Task 18 |
Wessler |
30126 |
$2,950.48 |
5/1/2017 |
Phase 3 Task 6 |
Wessler |
29776 |
$232.56 |
5/1/2017 |
Phase 4 Task 1 |
Wessler |
30123 |
$8,975.61 |
5/1/2017 |
Curb & Sidewalk Repair |
Ace in the Hole |
13126 |
$4,200.00 |
5/1/2017 |
Street Sweeping |
Envirosweep |
83431 |
$8,250.94 |
5/1/2017 |
Water Analysis |
Pace Analytical |
1750062002 |
$510.00 |
5/15/2017 |
Phase 3 Task 6 |
Wessler |
30123 |
$828.24 |
5/15/2017 |
Phase 1 Task 9 |
Wessler |
30165 |
$2,103.21 |
6/5/2017 |
Phase 3 task 6 |
Wessler |
30281 |
$375.35 |
6/5/2017 |
Phase 3 Task 5 |
Wessler |
30280 |
$2,539.90 |
6/5/2017 |
Phase 1 Task 9 |
Wessler |
30279 |
$1,171.39 |
6/5/2017 |
Phase 3 Task 18 |
Wessler |
30285 |
$2,887.60 |
6/5/2017 |
Phase 3 Task 17 |
Wessler |
30284 |
$1,517.50 |
6/5/2017 |
Phase 4 Task 1 |
Wessler |
30283 |
$4.026.25 |
6/5/2017 |
Sewer Pit 314 Grovewood |
Ace in the hole |
13133 |
$5,500.00 |
6/5/2017 |
Street Sweeping |
Envirosweep |
84069 |
$8,355.94 |
6/5/2017 |
Sewer Lining |
Miller Pipeline |
Sewer Lining |
$95,862.90 |